Energy · Crude oil export · Marine terminal, UK

VLCC berth gas removal

Client
UK crude oil export terminal operator
Asset
Offshore jetty berth loading VLCCs, with a manned control room on the platform
Our role
CDM Principal Contractor
Period
2020 – 2022

The challenge

When tankers load at the berth, hydrocarbon vapour vents from the ship and can drift across the jetty. On one berth it was reaching the air intake of the platform control room, which houses equipment that is not rated for explosive atmospheres. A previous HVAC trip had failed to stop gas entering the room, creating a serious ignition and explosion risk to people on the platform. The fix had to be designed and installed on a live export jetty, offshore, around ship loading operations and the weather.

What we did

  • Developed the scope and business case and secured investment approval
  • Re-engineered the control room ventilation with dual air intakes and fire dampers, so clean air is always drawn from the side away from the vapour
  • Upgraded the safety controls, with a new PLC control panel integrated with the site control system
  • Replaced the HVAC compressor and refrigerant as part of the same outage
  • Planned marine logistics and heavy lifts of new ductwork from a support vessel onto the jetty, with scaffold access built over the water
  • Managed design, fabrication, mechanical, E&I and controls contractors through isolations, destruct, installation and commissioning

Brownfield modification and decommissioning · Controls, automation and electrical · Project delivery and installation

Outcome

  • Both new air intakes installed, tested and commissioned, with the control system handed over as built
  • Gas ingress risk to the control room removed, closing out a significant process safety finding
  • Delivered offshore on a live crude export terminal, working around ship loading, isolations and the weather

Why it matters: a process safety risk to people on an offshore jetty, engineered out in one of the most exposed working environments in the industry.

More case studies: Offshore crane replacement · Glass recycling upgrade · Refinery flare line replacement · Fish farm pump upgrade · Offshore DMO switchgear replacement

Discuss your project →
Relevant experience

Need examples from your industry?

Tell us about your project and we will send a short selection of case studies that match it.

Request case studies