Client
Global pump manufacturer, for a leading salmon producer
Asset
Live freshwater salmon hatchery and its central water recirculation system
Our role
CDM Principal Contractor
Period
2026

The challenge

The hatchery's central recirculation system is its life support: every fish tank depends on a constant, controlled flow of oxygenated water. The ageing pump system wasted energy, worked against itself and gave operators no measurement of flow to individual tanks. Replacing it meant a full mechanical, electrical and controls upgrade on a live, welfare-critical site in a remote Highland location, within a short production shutdown that could not overrun without risk to stock.

What we did

  • Delivered the site works as Principal Contractor on a multi-discipline, turnkey energy optimisation package
  • Replaced the main pump set with high-efficiency, variable-speed units, marine-coated with stainless steel impellers
  • Re-engineered the pump room pipework: new baseplates, spool pieces, low-loss non-return valves and isolating valves tied into the existing manifold
  • Installed electromagnetic flow metering on every tank inlet and new pressure instrumentation across the manifold and oxygen cones
  • Integrated a new control and HMI panel with the existing site PLC and SCADA
  • Planned long-lead equipment around the shutdown, coordinated the equipment supplier and the mechanical, electrical and automation contractors on a remote site, and carried the job through to punch list close-out and commissioning

Project delivery and installation · Controls, automation and electrical · Plant reliability and improvement

Outcome

  • Mechanical, electrical, instrumentation and controls upgrade installed within the planned shutdown and handed over for commissioning
  • Full flow visibility and control at every tank for the first time
  • Designed to save around 340,000 kWh of electricity and 83 tonnes of CO2 a year, paying back in about three and a half years

Why it matters: a multi-discipline upgrade to life-support plant on a live, remote, welfare-critical site, delivered as one package with a clear payback in energy savings.

More case studies: Offshore crane replacement · Glass recycling upgrade · Refinery flare line replacement · Offshore DMO switchgear replacement · VLCC berth gas removal

Discuss your project →
Relevant experience

Need examples from your industry?

Tell us about your project and we will send a short selection of case studies that match it.

Request case studies