Glass recycling infrastructure upgrade
- Client
- International industrial minerals group
- Asset
- 24/7 glass recycling plant producing furnace-ready cullet for container glass makers
- Our role
- CDM Principal Contractor
- Period
- 2024 – 2025
The challenge
The plant was processing over 100,000 tonnes of glass a year but was available only around half the time, with more than 4,000 hours of downtime in a year. Wet, muddy kerbside glass blocked the front-end line, and the main sizing screen was end-of-life: its frame was cracking, repeated weld repairs were not holding, and its four stacked decks could only be cleaned with the whole plant stopped. A sudden failure would have meant months without production while a replacement was built.
What we did
- Analysed a full year of production and downtime records to find the real causes of lost hours
- Developed a portfolio of upgrades and the business cases for investment approval
- Replaced the four-deck sizer with two single-deck flip-flop screens that resist clogging and can be cleaned from outside
- Designed the new support steelwork, maintenance platforms and stairs for safe access
- Re-routed conveyors, chutes and dust extraction to suit the new layout
- Carried out the full installation with our own team, with the heavy lifts planned under LOLER and the new screens lifted in through the roof
Outcome
- End-of-life sizer removed and the new screening line installed and running in 2025
- Risk of a long, unplanned shutdown from a sudden screen failure taken away
- Screen cleaning moved from whole-plant stops to short, planned weekly checks
- Part of a wider upgrade portfolio designed to add more than 580 operating hours a year and process around 12,000 extra tonnes of glass
Why it matters: a data-led plan, approved and delivered on a live 24/7 plant, turning a known weak point into a reliable, safer-to-maintain line.